Last updated: October 2026
New home closing delays in Ontario are governed by the Statement of Critical Dates in your agreement’s Tarion Addendum. Builders can extend tentative closing dates only with at least 90 days’ written notice and within set limits. If they miss the firm closing date, you are entitled to delayed closing compensation of up to $7,500, including $150 per day for living expenses, and if the home is not finished by the outside closing date, you can terminate and get your money back with interest.
This guide by west-end REALTOR® Jason Polonski explains how delays work for freehold homes, what you can claim and how to protect your plans. It is based on Tarion’s delayed closing rules for freehold homes. It is general information, not legal advice; rules can change, so confirm details with Tarion and your lawyer. Condominium units follow a different set of occupancy rules.
| If the builder… | Your rights |
|---|---|
| Wants to move a tentative closing date | Must give written notice at least 90 days before that date, or it becomes your firm closing date |
| Misses the Firm Closing Date | $150 a day for living expenses plus receipted costs such as moving and storage, to a maximum of $7,500 |
| Gives less than 10 days’ notice of a delay | $1,500, equal to 10 days of living expenses |
| Hasn’t finished by the Outside Closing Date | A 30-day window to terminate, with a full refund of deposits, extras and upgrades plus interest |
| Asks you to sign a new closing date | Review it with your lawyer first; an amendment can waive compensation |
Each row is explained below. Source: Tarion’s delayed closing rules for freehold homes.
Every new freehold home agreement in Ontario includes a Tarion Addendum, and its first page is the Statement of Critical Dates. It tells you either:
All critical dates must be specific calendar dates that fall on business days.
For agreements with tentative dates, Tarion’s rules set out this sequence:
| Date | What it means |
|---|---|
| First Tentative Closing Date | The builder’s anticipated completion date |
| Second Tentative Closing Date | Up to 120 days after the first tentative date |
| Firm Closing Date | Up to 240 days after the first tentative date |
| Outside Closing Date | 365 days after the earlier of the second tentative date and the firm closing date |
To move past the First Tentative Closing Date, the builder must give you written notice at least 90 days before that date. If it does not, the first tentative date automatically becomes your Firm Closing Date. The same applies to the Second Tentative Closing Date: if the builder does not give notice at least 90 days before it, that date becomes firm.
This rule is the most useful tool you have for planning. Once a notice deadline passes without an extension, you know your firm date, and you can plan the sale of your current home, a lease ending or a school move with confidence.
Builders sometimes ask buyers to agree to a new closing date. Generally, at least 90 days’ written notice is required. Be careful: an amendment can waive compensation you would otherwise be entitled to. Read any proposed amendment with your lawyer before signing.
If the builder misses the Firm Closing Date, it must set a Delayed Closing Date and pay compensation. According to Tarion, compensation includes:
Compensation also applies if you terminate the agreement because of the delay.
The $7,500 maximum will not cover every cost of a long delay, such as months of rent, a second move, extra mortgage costs or a lost interest-rate hold. That is why planning around the outside dates, not the hoped-for date, matters so much.
If the home is not complete by the Outside Closing Date, you have a 30-day Purchaser’s Termination Period during which you can end the agreement. If you terminate because of the delay, you are entitled to a full refund of all money paid, including deposits, extras and upgrades, plus interest, along with delayed closing compensation.
Whether to terminate depends on the market. If prices have risen since you signed, closing late may still be your best option. If they have fallen, or your circumstances have changed, termination can be a valuable right. Talk to your lawyer before deciding.
Separate from delays, some agreements include early termination conditions, such as the builder needing certain approvals or meeting a project viability threshold. These allow the agreement to be terminated in specific circumstances described in the Addendum, with deposits returned. Read them before you sign, as explained in Jason’s builder purchase agreement guide.
According to Tarion:
Keep every notice the builder sends, along with receipts for moving, storage and other costs. Builders often pay compensation as a credit on the statement of adjustments at closing. Check that the amount is correct.
For move-up buyers, a delay after selling your current home is the scenario to plan for. Jason’s guide to selling your home while buying a new build covers strategies such as waiting for a firm date before listing, negotiating a rent-back with your buyer, or using bridge financing when dates are close.
A delay can push your closing past your mortgage rate hold or approval date. If your lender’s commitment expires, you may need to requalify, possibly at a different rate. Talk to your lender as soon as you receive a delay notice. The Financial Consumer Agency of Canada explains how rate holds and approvals work. Jason’s new build financing guide covers new-build specifics.
Ontario’s 2026 HST relief for qualifying new homes includes requirements related to the agreement date and construction timelines, according to Ontario’s program page. If your builder’s timeline changes significantly, ask your lawyer whether your eligibility is affected and what your agreement says about responsibility if a credited rebate is not available. The GST/HST new home rebate guide explains how the federal and Ontario programs fit together.
Common causes include municipal approvals and servicing, labour and material availability, weather, especially through Ottawa winters, and utility connections. Some causes are classified as unavoidable delays under the Addendum, such as certain events beyond the builder’s control, which can extend critical dates. Your lawyer can explain how the unavoidable delay provisions in your agreement work.
If you are buying a condominium unit, including stacked townhomes or flats sold as condominium units, the rules differ. Condominium purchases often involve an interim occupancy period, when you move in and pay occupancy fees before the condominium is registered and you take title. Tarion has separate rules for delayed occupancy of condominium units, and the Condo Authority of Ontario’s buyer’s guide explains the interim occupancy stage. Ask your lawyer to explain the critical dates in a condominium agreement specifically.
Once you close, delays are behind you and your new-home warranty begins. Tarion’s warranty information sheet for freehold homes sets out the one-, two- and seven-year coverage periods and the forms you need to submit. The Home Construction Regulatory Authority oversees builder licensing and conduct, and Tarion administers the warranty and deposit protection.
Jason tracks the critical dates for every new-build client, flags notice deadlines and plans the sale of their current home around them. When a builder issues a delay notice, he helps clients understand their options, works with their lawyer and lender, and adjusts the sale plan, including negotiating extended closings or rent-backs with their buyer. His Bachelor of Commerce, with a double major in Marketing and Finance from Concordia University, helps him walk clients through the financial impact of a delay, and he brings more than 15 years of Ottawa real estate experience and a background in the construction trades. He has helped hundreds of buyers and sellers across the west end. Learn more on the New Construction Realtor in Ottawa page, and see the Tarion warranty guide for what happens after closing.
Call or text (613) 601-9333 or email polonskiottawa@gmail.com. Read client reviews on his reviews page.
More on buying and selling at the same time: Coordinating Closing Dates | HELOC vs Bridge Loan | Sold Your House Before Buying
At least 90 days’ written notice before a tentative closing date. If no notice is given, that tentative date becomes the firm closing date.
Up to $7,500 in total, including $150 per day for living expenses and receipted costs such as moving and storage, if the builder misses the firm closing date.
If the home is not complete by the outside closing date, you have 30 days to terminate and receive all money paid, with interest, plus delayed closing compensation.
The latest date in the Statement of Critical Dates, 365 days after the earlier of the second tentative closing date and the firm closing date.
Only after legal advice. An amendment can waive compensation you would otherwise receive.
Claim with the builder within 180 days of closing or termination. If unresolved, claim with Tarion through MyHome within the deadlines Tarion sets.